Objectives
|
Outputs
|
Activities
|
Duration
|
Actor in-charge
|
Cost Estimate
|
- Strengthen the coordination unit. (Budget Line # 45.02)
|
- A fully functional equipment and server room
- A fully functional user help desk
- Sustainable user access to internet facilities
- A sustainable power source for operations
- Functional coordination unit offices
|
- Purchase and install air conditioning in equipment/server room
- Purchase and install blinds to cut out direct sunlight in equipment
room
- Purchase and install photocopier
- Purchase and install PABX
- Purchase and install safe and other cash office needs
- Purchase and install filing cabinet
- Procure 3 office chairs
- Pay bills:
- Establish 1998/99 staff contracts – 1 trip to LL for each staff member
for 2 days for tripartite meetings
- Purchase electricity generator for server room
|
|
- IS
- IS
- AA
- PC
- AA
- AA
- AA
- AA
- PC
- PC
|
- K23,895.00
- Quote needed
- K86940.00
- K63380.00
- K16794.00
- Quote
- Quote -5 office chairs)
- K11000.00
- K1700.00
- Direct payment
|
|
2. Management of CU offices
|
Smooth running of SDNP CU offices providing services to the public
|
- Maintain office supplies
- Administer project vehicle
- Order, purchase and install car radio & clock for project vehicle
MG168U
- Produce reports
|
3 months
|
- AA
- AA
- PC
- PC
- PC
|
- K12,000
- K33,000
- K5,000
|
- Enhance capacity within CU to execute and manage the project
(Budget Line # 30)
|
- Capacity for financial management
- An IS technically capable of establishing and running an Internet Hub
|
- Send AA on one week attachment to NRCM accounts department
- Send IS to attend a training workshop for Internet Node Operators for
two weeks in Zimbabwe at National University of Science and Technology,
Bulawayo
- Attend a NESU quarterly workshop
- Messenger issue
|
- one week
(9-15/8/98)
- August 30
(14 days)
- 3 days (19 August)
|
PC
|
1. K11490.00
2. K11,340)
3. K12,560
|
|
Establish an international Internet connection through the MPTC Satellite
Earth Station
(Budget Line # 021.01)
|
A functional international Internet connection
|
- Secure a written agreement with MPTC.
- Establish a working committee with MPTC and implement the connection
- Establish the physical leased line connection from Stadium Exchange
to Coordination Unit Offices plus interface equipment
- Secure an agreement with upstream ISP (UUNET)
- Monthly management of the international connection
|
3 months
|
1. PC
- PC
- PC
- PC
5. PC
|
1. Direct payment
2. Direct payment
3. K17000
4. Direct payment
5. Direct payment
|
|
6. Conduct a user and information source survey
(Budget Line # 030)
|
- An assessment of user information needs
- Data for a market survey
- Data on information sources
|
- Identify key users
- Identify key information providers or sources
- Send out about 300 questionnaires
- Characterize currently available data and information presentation
- Visit about 30 organizations nationwide for on site survey and questionnaire
follow up
- Identify requirements for Internet presentation of available data and
information
- Seek assistance from international volunteer agencies
|
1 month
|
PC
|
- –
- –
- K5,000
- –
- K25,000
- –
- –
|
|
7. Establish a legal framework for Malawi SDNP
(Budget Line # 11.01)
|
- A legally registered Malawi SDNP under the Companies Act of Malawi.
- Acceptable standing under MPTC requirements
|
- Engage a consultant lawyer to examine legal requirements
- Register Malawi SDNP as a legal entity under the Companies Act of Malawi
- Apply for a license from MPTC as a value added operator for Internet
Services
|
1 month
|
- PC
2. PC
|
Direct payment for legal fees under a consultancy
(K8000 PC travel)
|
- Plan a workshop for SDNP Internet users
(Budget Line # 030)
|
Up to 50 users trained
|
- Establish workshop requirements: programme, target group, equipment
resource persons, budget and venue
- Invite participants
- Run workshop (at Polytechnic during the long school break)
|
1 month
|
1. PC + IS
- AA
- PC
|
-
|
- Order equipment for regional hubs and install it.
(Budget Line # 047)
|
Delivered and installed computer servers with all Internet services
at regional centres
|
- Order and pay for the computers, routers, UPS, modems
- Deliver and install the equipment at the regional centers
|
3 months
|
- PC
- IS
|
- Direct payment
- K10,000
|
- Train Internet operators for two weeks
(Budget Line # 030)
|
Up to 10 node operators trained to run an Internet node
|
- Establish a functional training facilities including rooms, furniture,
computers and communications
- Organize training programme resource persons, materials
- Arrange transportation, accommodation and meals for node operators
- Supervise and manage training programmes
|
1 month
|
- IS
- PC
- AA
- PC
|
K148,500
($5,500)
|
- Establish pilot district nodes
|
6 district nodes able to access the Internet
|
- Coordinate the purchase of district node computers
- Install computers modems and telephone lines in node centres
- Set up e-mail and internet access
- Train node operators and users on site
|
1 month
|
- PC
- IS
- IS
4. IS
|
MK30000
(2 days on each site + travel)
|